The video illustrates the concept fantastically well. Mizoguchi has four plastic cups filled with sand. The sand in two of the cups is wet and frozen. In the others it’s dry. When he dumps water into the cups, it passes through the dry sand quickly, almost as if there was nothing in the cup. But when he dumps water on the frozen sand, it barely trickles out the bottom.

“Normal soil is composed of soil particles and water and air,” Mizoguchi tells me. The amount space between soil particles, known as its porosity, determines whether or not groundwater is allowed to pass through, he says. But when the water part of the soil is frozen, it expands to fill the open spaces, locking the soil bits in place, and the frozen ground becomes an impenetrable barrier to moving water. A groundwater barrier, like the kind to be used in Fukushima, is usually two or three meters thick, says Joseph Sopko, director of ground freezing for New Jersey-based engineering firm Moretrench. For mines and other sites where the frozen ground must act as a structural support, the wall can be more than ten meters thick.

Though the basic theory remains largely unchanged, computers have allowed engineers to construct more elaborate systems. This allows engineers like Sopko, who helped bring ground freezing into the computer age as a graduate student at Michigan State in the 1980s, to plan ground freezing projects in three dimensions.

Receive emails about upcoming NOVA programs and related content, as well as featured reporting about current events through a science lens.

Bigger Digging

Such advances would later help one of Sopko’s colleagues at Moretrench, David Mueller, during ground freezing operations for Boston’s Big Dig, an enormous infrastructure project that buried Interstate 93, an elevated eyesore which cut the city in half. The Big Dig was conceived in the 1970s and planning began in the early 1980s. Ground was broken in 1991. The final cost, including interest on borrowed funds, exceeded $24 billion.

While the Big Dig is infamous for its long timeline and inflated cost, there were a few bright spots, including the ground freezing operations. Engineers froze heaping portions of Boston’s soil solid. Mueller says Big Dig contractors chose artificial ground freezing because it offered the best way to excavate without risking subsidence, or a gradual shifting of the ground. It also minimized disruptions. Even as a 3.5 mile tunnel was carved through the heart of Boston, cars, buses, and trains continued to move along the roads and rails overhead.

“The design had to be absolutely right.”

“The real challenge on that particular project was working in and around all the Amtrak trains and their infrastructure. We had to install the system from within the tracks,” Mueller says. The complexity and scale of the Big Dig made it one of the—if not the —largest artificial ground freezing projects ever attempted in the U.S., he adds. “The design had to be right. The top of the tunnel was something like 10 feet below where the trains were.” That gave them enough ground to support the tracks above, but there wasn’t much room for error. “The design had to be absolutely right.”

A few hundred miles southwest, in New York City, engineers employed ground freezing on a smaller but similarly audacious project. The East Side Access, which is expected to be completed in 2018, will finally bring the Long Island Railroad to Grand Central Station in Manhattan. After zipping along Long Island, the trains will submerge to travel beneath the country’s busiest rail intersection, below the East River, and under some of the most expensive real estate in the world.

The tunnel under Northern Boulevard isn't long, but it was one of the most challenging parts of the East Side Access project. As work continued below, ice formed around the tunnel arch.

Every part of the project presented engineers with a different challenge, but perhaps the most vexing was the tunnel beneath Northern Boulevard in Queens. It was only 100 feet long, but it had to be built beneath a five-track subway, the four-lane Northern Boulevard, and a three-track elevated railway. The importance of the infrastructure above and the instability of the soil made ground freezing a no-brainer. “This is really soft ground,” says Michael Horodniceanu, president of MTA Capital Construction.

The top of the tunnel would be just 10 feet below the bottom of the subway tunnel. Ground freezing pipes were laid horizontally and uncomfortably close to the subway’s support piles. The proximity meant that engineers had to be aware not only of where they froze, but how the frozen soil would behave. Because the density of ice is lower than the density of liquid water, as soil freezes, it expands or swells. That expansion can cause cracks and create large, air-filled spaces. If this happens, the functionality of the frozen soil could be lost.

“During the freeze periods, we were very careful not to have to much heaving. When water freezes, it expands, and there’s a rail above,” Horodniceanu says. Avoiding complications meant testing and modeling the characteristics of the soil long before freezing began. “We knew the limits, and we were constantly making sure that we stayed below the limits,” Horodniceanu says. “It sounds exotic, but this is done every day.”

In the Long Run

At Fukushima, experts agree that the actual system won’t be all that exotic, either. The biggest challenge will be ensuring the safety of the workers who will install the expansive system of pipes and coolant needed to create a frozen barrier. “We don’t see anything from a technical standpoint that would preclude ground freezing from being used as a barrier. It seems like an appropriate use,” Mueller says. Rather, it’s the site’s dangerous radiation levels that could complicate matters, he adds.

For Fukushima, ground freezing isn’t a long-term solution, experts caution. Maintaining the barrier will require constant refrigeration, which requires a continuous source of power. Any interruption could compromise the barrier. Furthermore, powering the refrigeration units over a long period of time can be expensive. And in the case of Fukushima, it only contains the contamination—it doesn’t eliminate it. “I think it’s an appropriate thing to do. It is a smart thing to do,” Horodniceanu says. “But at the same time, the polluted water has to be extracted from the clean water.”

Providence CSO Raise Bore Shaft
Ground freezing keeps this shaft stable as work continues below on a sewer overflow project in Providence, Rhode Island.

The Japanese government is currently studying the frozen ground barrier proposal, and they expect to have a ground freezing system in place by April 2014, according to a document released in September by Japan’s Ministry of Economy, Trade and Industry. The proposed installation would encircle the four damaged reactors with an ice wall nearly one mile long and up to 100 feet deep, statistics that sound impressive but are quite achievable, Sopko points out. “It’s not a very challenging job, as far as depth goes,” he says. “The challenge is the men that have to drill the holes—keeping them safe, keeping them protected.”

Today, even this project seems normal to Sopko, but while in graduate school, he wouldn’t have predicted that ground freezing would be used to contain nuclear contamination. But after years of designing and creating ice walls, he now thinks that it could be used for “just about anything.” The current challenge, he says, isn’t about getting bigger. “I think we can handle the large projects, honestly.” Instead, he and others are hoping to shrink the process. “We’re looking at making smaller plants right now, and using it on smaller applications. How do we do a smaller job with less energy and more efficient freeze plants?” When that happens, ground freezing could really heat up.

Photo credits: Greg Webb/IAEA , Moretrench, and MTAphotos/Flickr (CC-BY)

Share this article

Major funding for NOVA is provided by the David H. Koch Fund for Science, the NOVA Science Trust, the Corporation for Public Broadcasting, and PBS viewers.